Coronavirus - Special OCA Bulletin (3/6/2020)

Please see several resources below that we wanted to share related to the Coronavirus situation as it relates to Ohio. There are currently no reported cases in Ohio but this information helps provide answers on how to reduce the spread of the virus, help protect employees from contracting the virus if it is found in Ohio and possible impacts on projects due to delays. 

Please share with OCA if your company experiences any delays of materials due to supply chain disruptions as a result of the virus elsewhere so that we can help monitor the situation.


State of Ohio - Coronavirus Resources and Prevention Information 


It is important to note that according to the federal Centers for Disease Control and Prevention, the risk to the general public in most communities is currently considered low. There have been no confirmed cases of COVID-19 in Ohio.

Here are several resources you can use to ensure your community is getting accurate, up-to-date information and that they are practicing proven prevention methods:

• You can access coronavirus.ohio.gov for constantly-updated information and guidance.

• Read the most accurate information on COVID-19 in this fact sheet (HERE) from the federal CDC.

• You can post this prevention infographic (HERE) on Twitter or Facebook or hang it on community bulletin boards in community buildings.

   AGC - Industry Specific Guidance and Resources

Comprehensive AGC Information Page

Media Talking Points

FHWA Response to Coronavirus Disruptions to On-Going Construction Projects

Below is FHWA’s response to AGC’s inquiry concerning project delays due to coronavirus circumstances. A discussion with your state DOT regarding its delay policies may provide more insight. Further guidance from FHWA may be forthcoming. 


Q: What is FHWA’s position on project delays resulting from potential material shortages or quarantines of project locations due to the coronavirus?

A: FHWA expects the States to be consistent with their policies and contract language relating to delays and material shortages. Most State DOT standard specifications address time extensions and how material shortages may be considered under their contract terms.

Some states may grant excusable, non-compensable time extensions when a contractor experiences extraordinary delays in material delivery or project site quarantines. While the attached file is now more than 10 years old, it shows that many states had policies for granting excusable non-compensable time extensions when unusual market conditions are present.

State DOT examples follow:
Minnesota Standard specification 1806.2
1806.2 TYPES OF DELAYS A Excusable, Non-Compensable Delays

Excusable, non-compensable delays are delays that are not the Contractor’s or the Department’s fault or responsibility, and that could not have been foreseen by the Contractor. The Department will not compensate the Contractor for excusable, non-compensable delays. Excusable, non-compensable delays include, but are not limited to:
(1) Delays due to fires, floods, tornadoes, lightning strikes, earthquakes, epidemics, or other cataclysmic phenomena of nature.
(2) Delays due to weather if the Contractor is entitled to a time extension for weather as specified in 1806.3, “Determination of Charges on Working Day Contracts,” and 1806.4, “Extension of Contract Time Due to Weather on Calendar Day and Completion Date Contracts.” (3) Extraordinary delays in material deliveries the Contractor or its suppliers cannot foresee or avoid resulting from freight embargoes, government acts, or regional material shortages.
(4) Delays due to civil disturbances.
(5) Delays due to acts of the public enemy.
(6) Delays due to labor strikes that are beyond the Contractor’s, subcontractor’s, or supplier’s power to settle and are not caused by improper acts or omissions of the Contractor, subcontractor, or supplier.
(7) Delays due to acts of the government or a political subdivision other than the Department. (8) All other delays not the Contractor’s or Department’s fault or responsibility and which could not have been foreseen by the Contractor.

Kansas standard specifications (108.5c(5)) only approves non-compensable excusable delays for national material shortage defined as
108.5(d)(5):
5) National Material Shortages. The Engineer will not charge working days under subsection 108.5c.(5) if there is a national material shortage unless:
• the national material shortage was foreseeable at the time of bid; or
• the national material shortage does not prevent the Contractor from performing the CIOW